New roads in New Stanton: 3 roundabouts could debut this week

| Monday, Feb. 20, 2017, 10:33 p.m.

Motorists in New Stanton could be using three new roundabouts this week.

The circular intersections are tentatively set to open Friday as part of improvements along the Interstate 70 corridor, said Dominec Caruso, a PennDOT assistant construction manager.

Two roundabouts are part of a redesigned I-70 interchange that has been shifted west from its previous location. They will allow drivers to detour around a section of Center Avenue that is scheduled for closure in early March to allow for improvements and replacement of a bridge that crosses the interstate.

Caruso said construction of the roundabout system essentially is complete.

“There are still overhead sign structures that have to be updated, some things we need to do before we can make sure it functions,” he said.

To relieve congestion on streets north of the interstate, PennDOT connected Rachel Drive to Bair Boulevard with a third roundabout. It will be turned over to the borough.

Officials say roundabouts ease traffic flow by replacing stop signs or signals with yielding movements and improve safety by eliminating left turns. Drivers move counter-clockwise through a roundabout, yielding to traffic within the intersection before entering. A right-turn signal should be displayed before exiting.

The interchange roundabouts are paired via a two-way connection running beneath I-70. The northernmost of the pair has a teardrop shape rather than a circular one because one of the connecting roads is an off-ramp for westbound I-70 traffic that motorists can't enter from the roundabout.

According to Caruso, it should take contractor Joseph B. Fay Co. about three weeks to demolish the Center Avenue bridge. As work continues there, crews will shift south by early April to close and replace a second bridge that carries the street over Sewickley Creek. Fay project manager Jason Sinay has said replacement of the bridge over I-70 should be completed within 100 days while work on the creek crossing is expected to take up to 130 days.

PennDOT's official detour for the creek bridge closure will have motorists use Technology Drive and Route 119. The closure will trigger a change in emergency response plans for the New Stanton Volunteer Fire Department, which has its station north of the bridge, and for Mutual Aid Ambulance Service, with a station south of the span.

During construction, the fire department will move one of its trucks south of the bridge, stationing it at the borough building, and will have a crew available on that side of the creek, Chief Rob Cammarata said. Three other fire vehicles will remain at the station.

Cammarata said the department will work with the ambulance service as it makes contingency plans for the bridge closure.

“If they need to stand by with an ambulance unit, we'll have a free bay for them,” he said.

According to New Stanton Councilman Dean Clark, Mutual Aid has asked for temporary removal of one speed bump on Thermo Village Road and another on Pine Drive, roads ambulance units likely will use during the bridge closure. Fay is expected to remove and later restore the bumps, Clark said.

At least half a dozen residents of New Stanton Commons and Huntingdon Village apartments in adjacent East Huntingdon use the Sewickley Creek bridge to walk to work.

A Westmoreland County Transit Authority bus travels in that vicinity every two hours and, as part of upcoming route adjustments, should be able to divert along Sunny Lane to serve residents of the housing complexes, Director of Operations Meghan Yuhouse said.

Fay is scheduled to complete its work at New Stanton by Oct. 28. This year's work schedule also will include reconstruction of a section of I-70 between the old New Stanton off-ramps and the Pennsylvania Turnpike interchange. Construction will be phased so that traffic can be maintained on the interstate.

Tribune-Review staff writer Matthew Santoni contributed. Jeff Himler is a Tribune-Review staff writer. Reach him at 724-836-6622 or jhimler@tribweb.com.

TribLIVE commenting policy

You are solely responsible for your comments and by using TribLive.com you agree to our Terms of Service.

We moderate comments. Our goal is to provide substantive commentary for a general readership. By screening submissions, we provide a space where readers can share intelligent and informed commentary that enhances the quality of our news and information.

While most comments will be posted if they are on-topic and not abusive, moderating decisions are subjective. We will make them as carefully and consistently as we can. Because of the volume of reader comments, we cannot review individual moderation decisions with readers.

We value thoughtful comments representing a range of views that make their point quickly and politely. We make an effort to protect discussions from repeated comments either by the same reader or different readers

We follow the same standards for taste as the daily newspaper. A few things we won't tolerate: personal attacks, obscenity, vulgarity, profanity (including expletives and letters followed by dashes), commercial promotion, impersonations, incoherence, proselytizing and SHOUTING. Don't include URLs to Web sites.

We do not edit comments. They are either approved or deleted. We reserve the right to edit a comment that is quoted or excerpted in an article. In this case, we may fix spelling and punctuation.

We welcome strong opinions and criticism of our work, but we don't want comments to become bogged down with discussions of our policies and we will moderate accordingly.

We appreciate it when readers and people quoted in articles or blog posts point out errors of fact or emphasis and will investigate all assertions. But these suggestions should be sent via e-mail. To avoid distracting other readers, we won't publish comments that suggest a correction. Instead, corrections will be made in a blog post or in an article.