Greater Latrobe will replace part of senior high roof, refinish gym floor

Jeff Himler
| Wednesday, May 16, 2018, 12:12 a.m.
Greater Latrobe Senior High School, built in the mid-1960s, is seen in a 2017 view.
Jeff Himler | Tribune-Review
Greater Latrobe Senior High School, built in the mid-1960s, is seen in a 2017 view.

Greater Latrobe School District will spend $2.6 million to replace more than half of its senior high school roof over two summers.

The school board this week awarded the roof installation to Tuscano-Maher Roofing of Saltsburg for nearly $1.8 million, the lowest of three proposals received. The district will buy job materials from Garland/DBS Inc. of Cleveland, Ohio, at a cost of $835,519.41, excluding freight.

Kurt Thomas, the district's director of facilities, operations and planning, said he's happy with the costs, which are within 4 percent of estimates.

The project will replace about 120,000 square feet of material that was installed in 1993, over the building's original 1966 roof, and is expected to resolve three leaks, he said. It will update the roof in all areas save the gym, the auditorium and one classroom wing — which were included in a 2001 renovation.

The board agreed to pay $32,230 to Miller Flooring Company to refinish the wood floor of the main senior high gym. The firm will have five weeks this summer to complete the job, Thomas said, noting the auxiliary gym will be available if school athletes need it for practice sessions.

In a previous report to the board, Thomas noted the floor had received a new top coating but was never fully refinished since it was installed in 2001. “This process should occur every 12-15 years,” he wrote, explaining the steps after sanding include “applying a seal, paint and finish to restore the wood floor, to ensure the long life and performance.”

The board contracted with Maroadi Transfer and Storage to move equipment and materials from the current Latrobe Elementary School to the new two-story version of the school that is under construction several blocks away on Ligonier Street and is slated to open for the fall semester. The company will charge $53,085 for its services.

Project site manager George Dickerson reported that crews are expected this month to complete the new school's stone and brick veneer while beginning to hang drywall in main corridors, install kitchen equipment and place flooring and ceiling tiles in classroom wings.

Jeff Himler is a Tribune-Review staff writer. Reach him at 724-836-6622, jhimler@tribweb.com or via Twitter @jhimler_news.

TribLIVE commenting policy

You are solely responsible for your comments and by using TribLive.com you agree to our Terms of Service.

We moderate comments. Our goal is to provide substantive commentary for a general readership. By screening submissions, we provide a space where readers can share intelligent and informed commentary that enhances the quality of our news and information.

While most comments will be posted if they are on-topic and not abusive, moderating decisions are subjective. We will make them as carefully and consistently as we can. Because of the volume of reader comments, we cannot review individual moderation decisions with readers.

We value thoughtful comments representing a range of views that make their point quickly and politely. We make an effort to protect discussions from repeated comments either by the same reader or different readers

We follow the same standards for taste as the daily newspaper. A few things we won't tolerate: personal attacks, obscenity, vulgarity, profanity (including expletives and letters followed by dashes), commercial promotion, impersonations, incoherence, proselytizing and SHOUTING. Don't include URLs to Web sites.

We do not edit comments. They are either approved or deleted. We reserve the right to edit a comment that is quoted or excerpted in an article. In this case, we may fix spelling and punctuation.

We welcome strong opinions and criticism of our work, but we don't want comments to become bogged down with discussions of our policies and we will moderate accordingly.

We appreciate it when readers and people quoted in articles or blog posts point out errors of fact or emphasis and will investigate all assertions. But these suggestions should be sent via e-mail. To avoid distracting other readers, we won't publish comments that suggest a correction. Instead, corrections will be made in a blog post or in an article.

click me