Sweaty pipes force expensive emergency repairs at North Allegheny elementary school | TribLIVE.com
North Hills

Sweaty pipes force expensive emergency repairs at North Allegheny elementary school

Tony LaRussa
1577062_web1_WEB-North-Allegheny-Hosack-Elementary-School

The North Allegheny School Board on Wednesday unanimously approved a nearly $450,000 contract for emergency repairs to the cooling system at Hosack Elementary School in McCandless.

The $448,210 contract was awarded to George V. Hamilton Inc. of McKees Rocks, which was the only company to submit a bid for the work from a pool of seven companies that were contacted by the district, said Rob Gaertner, the district’s director of project management.

“Several (companies) said they did not have the manpower to take on this work at this time,” Gaertner said, adding that the state Department of Education allowed the district to seek bids without the required public advertising because of the emergency nature of the project.

Gaertner said the problem was discovered while looking for the source of stains that appeared on the building’s ceiling tiles.

“Upon further investigation we found that the chilled water pipe insulation was failing and causing condensation to occur on the exterior of the pipes that was dripping on the tile,” he told the school board during its Aug. 21 meeting.

The project involves removal and disposal of the old ceiling tile and insulation throughout the first floor and in part of the second floor; installing new pipe hangers to accommodate thicker, more robust insulation; and installing new tiles.

A series of air quality tests are being conducted during the project to ensure that no mold is present as a result of the insulation failure, said Roger Sechler, the district’s director of operations.

“The air quality in the building was never a danger,” he said. “If we let it go it can become bad, but we caught it.”

Sechler said portable air conditioning units will be placed in the building to remove moisture and provide cooling until the project is completed and the main cooling system can be turned on. The work is expected to take several weeks to complete.

District students are scheduled to return to classes on Aug. 27.

Tony LaRussa is a Tribune-Review staff writer. You can contact Tony at 724-772-6368, [email protected] or via Twitter .

Categories: Local | North Hills
TribLIVE commenting policy

You are solely responsible for your comments and by using TribLive.com you agree to our Terms of Service.

We moderate comments. Our goal is to provide substantive commentary for a general readership. By screening submissions, we provide a space where readers can share intelligent and informed commentary that enhances the quality of our news and information.

While most comments will be posted if they are on-topic and not abusive, moderating decisions are subjective. We will make them as carefully and consistently as we can. Because of the volume of reader comments, we cannot review individual moderation decisions with readers.

We value thoughtful comments representing a range of views that make their point quickly and politely. We make an effort to protect discussions from repeated comments either by the same reader or different readers

We follow the same standards for taste as the daily newspaper. A few things we won't tolerate: personal attacks, obscenity, vulgarity, profanity (including expletives and letters followed by dashes), commercial promotion, impersonations, incoherence, proselytizing and SHOUTING. Don't include URLs to Web sites.

We do not edit comments. They are either approved or deleted. We reserve the right to edit a comment that is quoted or excerpted in an article. In this case, we may fix spelling and punctuation.

We welcome strong opinions and criticism of our work, but we don't want comments to become bogged down with discussions of our policies and we will moderate accordingly.

We appreciate it when readers and people quoted in articles or blog posts point out errors of fact or emphasis and will investigate all assertions. But these suggestions should be sent via e-mail. To avoid distracting other readers, we won't publish comments that suggest a correction. Instead, corrections will be made in a blog post or in an article.