North Hills months behind West View Elementary captured vestibule project

Tony LaRussa
| Monday, Oct. 8, 2018, 5:57 p.m.
A project to construct a “capture vestibule” to prevent people from easily entering the West View Elementary School building has been delayed by the need to custom fabricate some of its components. The project was expected to be done by the start of the school year but won’t be completed until early November, according to the architect who designed the system.
A project to construct a “capture vestibule” to prevent people from easily entering the West View Elementary School building has been delayed by the need to custom fabricate some of its components. The project was expected to be done by the start of the school year but won’t be completed until early November, according to the architect who designed the system.

Efforts to improve the security at the West View Elementary School building by reconfiguring the main entrance have been hampered by delays in obtaining custom-fabricated components needed for the project, according to the project’s architect.

In April the North Hills school board agreed to add a so-called “capture vestibule” to the building that would serve as a secure holding area to prevent anyone who comes through the front doors from venturing farther into the building.

The work was supposed to be completed by the time students returned from summer break in late August.

But the project is not expected to be completed until early November, according to Jon Thomas of Thomas & Williamson Program Management, which designed the vestibule.

“In past years we’ve done projects where we’ve done everything we could to use off-the-shelf materials,” Thomas said, noting that much of the material for the expansion at McIntyre Elementary were easily obtained “so we didn’t have any fabrication going on to slow down the progress.”

“With this project, we didn’t have that luxury,” Thomas said.

Some of the items that have to be made-to-order include a skylight, the glass and metal “storefront” that serves as the main structure of the vestibule, as well as doors and windows.

Thomas said weather also has impacted progress.

“The roofing and sheet metal trim has been ready to go (since the end of September),” he said, adding that contractors have been trying to do the work “in between rainstorms.”

Adding the capture vestibule to serve as a secure holding area is part of the district’s efforts to bolster the safety of students and staff.

Once the captured vestibule is completed, visitors will be buzzed in and then wait in an enclosed area equipped with bulletproof glass until their credentials are checked.

Although considered a small project, Thomas said creating the vestibule has also been made “challenging” because the original entrance to the building is not accessible for people with physical limitations.

As a result, contractors had to construct modifications to allow people who use wheelchairs to enter the building.

Several board members were upset that the project is not done.

“This is really frustrating on the part of the board because we spent an awful lot of time thinking about how to make our students safer,” said board member Annette Giovengo-Nolish. “This is something that we agreed on last spring.”

While Thomas acknowledged the board’s frustration, he said the delays in obtaining materials is beyond the scope of his contract for the project.

He said while he typically performs construction management as part of the work he does for the district, for this project he was only hired to do the design work.

“I have some regular check-ins (with the contractors) and don’t charge for that,” he said, adding that he also has not billed the district for time spent appearing before the board to provide updates or answer questions.

But “we‘re not doing procurement management and monitoring the purchase of materials,” he said. “You didn’t hire me to do that here.”

Tony LaRussa is a Tribune-Review staff writer. You can contact Tony at 724-772-6368 or tlarussa@tribweb.com or via Twitter @TonyLaRussaTrib.

TribLIVE commenting policy

You are solely responsible for your comments and by using TribLive.com you agree to our Terms of Service.

We moderate comments. Our goal is to provide substantive commentary for a general readership. By screening submissions, we provide a space where readers can share intelligent and informed commentary that enhances the quality of our news and information.

While most comments will be posted if they are on-topic and not abusive, moderating decisions are subjective. We will make them as carefully and consistently as we can. Because of the volume of reader comments, we cannot review individual moderation decisions with readers.

We value thoughtful comments representing a range of views that make their point quickly and politely. We make an effort to protect discussions from repeated comments either by the same reader or different readers

We follow the same standards for taste as the daily newspaper. A few things we won't tolerate: personal attacks, obscenity, vulgarity, profanity (including expletives and letters followed by dashes), commercial promotion, impersonations, incoherence, proselytizing and SHOUTING. Don't include URLs to Web sites.

We do not edit comments. They are either approved or deleted. We reserve the right to edit a comment that is quoted or excerpted in an article. In this case, we may fix spelling and punctuation.

We welcome strong opinions and criticism of our work, but we don't want comments to become bogged down with discussions of our policies and we will moderate accordingly.

We appreciate it when readers and people quoted in articles or blog posts point out errors of fact or emphasis and will investigate all assertions. But these suggestions should be sent via e-mail. To avoid distracting other readers, we won't publish comments that suggest a correction. Instead, corrections will be made in a blog post or in an article.

click me