PennDOT updates status of road projects

| Thursday, May 10, 2012, 2:09 a.m.

PennDOT District 12 has announced the status of several road repair projects in the area as of Sept. 29.

In Westmoreland County:

  • The second phase of major construction continues on Route 22 in Murrysville. Mainline Route 22 traffic continues to use the newly reconstructed eastbound and westbound lanes. Major intersections are controlled with temporary traffic signals. The $29.8 million project is being done in 10 phases.

    Closings of other side streets (McCloy Avenue, Carson Avenue, Branthoover Cutoff, Laird Drive, School Road and Cozy Inn) occur as construction proceeds in a west to east direction.

    One-lane traffic patterns continue in eastbound lanes from Technology Drive to Andrews Drive and on both the eastbound and westbound lanes from Andrews Drive to Plaza Drive.

  • Utility work is completed along the main line of Route 30 in the $1.4 million project to widen the roadway to five lanes near the Norwin Towne Square Shopping Center.

    The westbound lanes along Route 30 are reduced to a single lane through December. Drain installation is starting in the slow lane. Crews also are working on installing new traffic signals throughout the project area.

    Route 30 will be reopened to unrestricted traffic flow in the winter, but the project will resume in April. The project is expected to be completed in November 2005.

  • Paving continues in the $2.3 million restoration of Route 31 from the Route 119 interchange to First Street in East Huntingdon Township and Mt. Pleasant. Miscellaneous repairs are being completed throughout the project area. Traffic continues to be restricted to one lane in each direction.

    A reduced speed limit of 35 miles per hour is in effect during construction.

  • The $6.28 million reconstruction of the Apollo Bridge is awaiting design approvals. Work will include reconstruction of the bridge in Oklahoma Borough and Apollo over the Kiskiminetas River and the complete reconstruction of intersecting state routes and borough roads.

  • Lattanzio Road, the Lattanzio Road Extension, Allvac Plant entrance and the Industrial Park plant entrance remain closed as a result of the state Route 981 reconstruction project. Motorists must use the official posted detour route using Route 22, Route 982 and Latrobe-Derry Road.

    The $2.8 million project in Derry Township includes lowering the grade under the Norfolk Southern Railroad line and replacing the bridge carrying Route 981 over Saxman Run immediately north of Latrobe-Derry Road.

  • The left lanes of Route 30 eastbound and westbound will be closed from North Greengate Road to Everglade Road in Hempfield Township from Oct. 6-31. While the lanes are closed, paving will take place, islands will be removed and turning lanes installed. The work is part of the developer's project at the former Greengate Mall site.

    In Fayette County:

  • There are no traffic restrictions as a result of the $25 million replacement of the Yough Dam Bridge. The new bridge will be located immediately north of the existing bridge. Two lanes of traffic will be maintained during construction with occasional single-lane closures controlled by flaggers.

  • Milling will begin on Prison Road, in Luzerne Township. The $1.3 million project includes base repair, shoulder paving, drainage upgrades, guide rail work, widening and resurfacing from the intersection of East Millsboro Road to the Fayette County Prison entrance.

  • TribLIVE commenting policy

    You are solely responsible for your comments and by using TribLive.com you agree to our Terms of Service.

    We moderate comments. Our goal is to provide substantive commentary for a general readership. By screening submissions, we provide a space where readers can share intelligent and informed commentary that enhances the quality of our news and information.

    While most comments will be posted if they are on-topic and not abusive, moderating decisions are subjective. We will make them as carefully and consistently as we can. Because of the volume of reader comments, we cannot review individual moderation decisions with readers.

    We value thoughtful comments representing a range of views that make their point quickly and politely. We make an effort to protect discussions from repeated comments either by the same reader or different readers

    We follow the same standards for taste as the daily newspaper. A few things we won't tolerate: personal attacks, obscenity, vulgarity, profanity (including expletives and letters followed by dashes), commercial promotion, impersonations, incoherence, proselytizing and SHOUTING. Don't include URLs to Web sites.

    We do not edit comments. They are either approved or deleted. We reserve the right to edit a comment that is quoted or excerpted in an article. In this case, we may fix spelling and punctuation.

    We welcome strong opinions and criticism of our work, but we don't want comments to become bogged down with discussions of our policies and we will moderate accordingly.

    We appreciate it when readers and people quoted in articles or blog posts point out errors of fact or emphasis and will investigate all assertions. But these suggestions should be sent via e-mail. To avoid distracting other readers, we won't publish comments that suggest a correction. Instead, corrections will be made in a blog post or in an article.

    click me