On the advice of their architect, Fayette County commissioners on Thursday rejected all bids for construction of a minimum-security prison building.

Architect Michael Molnar told the commissioners his estimates of construction costs had been done before the site had been thoroughly studied. He said the foundation and a large retaining wall had increased his initial estimates.

'Bids came in quite a bit higher,' Molnar said. 'Therefore, I recommend the commissioners reject all bids for general construction.'

Molnar then gave the commissioners a plan to rebid the project that would not throw it too far behind schedule.

'Because this problem was my fault, I will redo all plans free of charge,' Molnar said. 'I'm certain they will be much closer to the original cost.'

Molnar said he could have plans ready for readvertising on Sunday, with specifications available on Monday.

'The way I have it scheduled, we could open bids on Oct. 30,' he said.

All three commissioners expressed concern for the timetable of the project.

'We have about 35 prisoners in other counties at about $35 per day for each,' said Commissioner Vince Vicites. 'Surely in this case, time is money.'

Molnar said he expects to be able to reduce the original bid by about $200,000.

One item he cited that could be eliminated was a building-wide emergency generator to be used in case of a power failure.

'That's about $35,000,' he said. 'You can have emergency lighting, but you don't need it all over.'

After Molnar left the meeting, Commissioner Ron Nehls took exception to the change.

'I'm not sure we shouldn't have that generator in there,' he said. 'We can't afford to delay this project any more. We have to move this forward.'

Commissioner Vicites said bids will be accepted and opened on Oct. 30 and a special meeting called soon afterward to act on the bids.

In other business, the commissioners:

  • Approved the purchase of two X-ray scanners for use in the courthouse and public safety building at a cost of $20,649 each. 'I think this is the prudent thing to do in the times we live in,' Commissioner Sean Cavanagh said.

  • Hired William Piper as a county consultant to assist the commissioners in administration of the 12-year-transportation program at a rate of $60 per hour. Piper had 30 years of experience with PennDOT. Vicites had been against placing the item on the agenda but said that after the meeting with Piper he was very much in favor of him. 'It wasn't the man, but the manner in which it was presented,' he said.

  • TribLIVE commenting policy

    You are solely responsible for your comments and by using TribLive.com you agree to our Terms of Service.

    We moderate comments. Our goal is to provide substantive commentary for a general readership. By screening submissions, we provide a space where readers can share intelligent and informed commentary that enhances the quality of our news and information.

    While most comments will be posted if they are on-topic and not abusive, moderating decisions are subjective. We will make them as carefully and consistently as we can. Because of the volume of reader comments, we cannot review individual moderation decisions with readers.

    We value thoughtful comments representing a range of views that make their point quickly and politely. We make an effort to protect discussions from repeated comments either by the same reader or different readers

    We follow the same standards for taste as the daily newspaper. A few things we won't tolerate: personal attacks, obscenity, vulgarity, profanity (including expletives and letters followed by dashes), commercial promotion, impersonations, incoherence, proselytizing and SHOUTING. Don't include URLs to Web sites.

    We do not edit comments. They are either approved or deleted. We reserve the right to edit a comment that is quoted or excerpted in an article. In this case, we may fix spelling and punctuation.

    We welcome strong opinions and criticism of our work, but we don't want comments to become bogged down with discussions of our policies and we will moderate accordingly.

    We appreciate it when readers and people quoted in articles or blog posts point out errors of fact or emphasis and will investigate all assertions. But these suggestions should be sent via e-mail. To avoid distracting other readers, we won't publish comments that suggest a correction. Instead, corrections will be made in a blog post or in an article.

    click me