New Kensington bridge opening delayed

| Monday, Aug. 13, 2007

Valley High School students who usually ride to school across the Seventh Street Bridge will have to adjust to a detour for at least the first month of school.

PennDOT spokeswoman Valerie Petersen said the bridge in New Kensington was scheduled to be completed by Aug. 28 before school started but after a delay in receiving a part, the bridge will remain closed until the end of September.

New Kensington-Arnold School District superintendent George Batterson said buses that normally cross the bridge will have to be rerouted and some students will have to get their bus at a different stop.

A pedestrian walkway will be open over the bridge, but no vehicles will be able to cross.

He said the district learned of the problem in the middle of last week but will adjust to the situation.

Batterson said the district will notify students of the change soon.

Students living in Arnold and the downtown and some hill sections of New Kensington are likely to be most affected since Seventh Street provides the quickest vehicle access to the high school for them.

The aging bridge spans Puckety Creek, near the intersection of Seventh Street and Stevenson Boulevard (Route 366). It was closed June 8 so the entire structure could be replaced.

Bill Lowry, assistant construction executive for PennDOT District 12, which includes Westmoreland County, said prior to the start of construction that the agency wanted to complete the $582,000 project before the start of school.

"We talked about holding that (the start) off until after the U.S. Open, but we made a commitment to get that thing replaced before school starts," Lowry said at the end of May. The U.S. Open Golf Championship at the Oakmont Country Club began the week of June 11 and was the focus of traffic concerns in the area.

Although other work on the bridge can be done, the wait for the part will push the completion day back three or four weeks, Petersen said.

She said PennDOT has been in communication with the school district and the police department to coordinate the start of school.

The official detour leads through the Parnassus Triangle though many vehicles use Linden Avenue to bypass the closure.

TribLIVE commenting policy

You are solely responsible for your comments and by using TribLive.com you agree to our Terms of Service.

We moderate comments. Our goal is to provide substantive commentary for a general readership. By screening submissions, we provide a space where readers can share intelligent and informed commentary that enhances the quality of our news and information.

While most comments will be posted if they are on-topic and not abusive, moderating decisions are subjective. We will make them as carefully and consistently as we can. Because of the volume of reader comments, we cannot review individual moderation decisions with readers.

We value thoughtful comments representing a range of views that make their point quickly and politely. We make an effort to protect discussions from repeated comments either by the same reader or different readers

We follow the same standards for taste as the daily newspaper. A few things we won't tolerate: personal attacks, obscenity, vulgarity, profanity (including expletives and letters followed by dashes), commercial promotion, impersonations, incoherence, proselytizing and SHOUTING. Don't include URLs to Web sites.

We do not edit comments. They are either approved or deleted. We reserve the right to edit a comment that is quoted or excerpted in an article. In this case, we may fix spelling and punctuation.

We welcome strong opinions and criticism of our work, but we don't want comments to become bogged down with discussions of our policies and we will moderate accordingly.

We appreciate it when readers and people quoted in articles or blog posts point out errors of fact or emphasis and will investigate all assertions. But these suggestions should be sent via e-mail. To avoid distracting other readers, we won't publish comments that suggest a correction. Instead, corrections will be made in a blog post or in an article.

click me