The 2026 NFL Draft in Pittsburgh is over, but some roads remain closed as crews tear down the infrastructure set up during the three-day event.
By May 11, things should be back to normal.
There are three phases of road closures left in the initial six-phase plan that was announced ahead of the draft by transportation leaders and city officials.
Phase 4 began Sunday and will last through Friday. The following roads are still closed during that time:
- Casino Drive (from Sproat Way)
- North Shore Drive (to Chuck Noll Way)
- Reedsdale Street (to Tony Dorsett Drive)
- Chuck Noll Way
- Tony Dorsett Drive
- Interstate 279 Southbound Exit 1B
These roads are in addition to the Phase 1 closures, which include:
- Art Rooney Avenue
- West General Robinson Street (to Tony Dorsett Drive)
- Scotland Avenue
Following Phase 4, the last two phases will be as follows:
- Phase 5 closures (May 2-6): Reedsdale Street, Chuck Noll Way, Tony Dorsett Drive, along with the closures in Phase 1 (Art Rooney Avenue, West General Robinson Street to Tony Dorsett Drive and Scotland Avenue)
- Phase 6 closures (May 7-10): Art Rooney Avenue, West General Robinson Street (to Tony Dorsett Drive), Scotland Avenue